Central Avenue - West City Line to Everett Road - Road reconstruction - Utility Work continues through May 1, 2008
Gas Main replacement: *** Updated ***
The work hours will be from 6PM - 6AM each night Sunday through Friday nights. The contractor will be replacing the gas main on the south side of Central Avenue starting at King Ave and working west in the eastbound curb lane. A single eastbound lane closure will be set up during the work hours. Additionally limited off roadway work will be performed Monday - Friday during the daytime hours.
Overhead utility replacement:
This work continues daily between 7AM and 7PM on Central Avenue eastbound and westbound between the west City line and Colvin Avenue. The contractor for National Grid is working off roadway to set new utility poles. Minimal impacts to the eastbound traffic during this work.
Various other overhead utility companies will have right eastbound or westbound lane closures between 9AM and 3 PM daily to relocated their utility lines.
Courtesy of:
William E. Trudeau Jr.
Coordinator
City of Albany
Traffic Engineering
526 Central Avenue
Albany, New York 12206
No comments:
Post a Comment