Wednesday, October 3, 2007

City of Albany Roadwork update September 29 - October 5 2007

Central Avenue - West City Line to Everett Road - Road reconstruction - Utility Work continues through May 1, 2008

Gas Main replacement: *** Updated ***

The work hours will be from 6PM  - 6AM each night Sunday through Friday nights.  The contractor will be replacing the gas main on the south side of Central Avenue starting at King Ave and working west in the eastbound curb lane.  A single eastbound lane closure will be set up during the work hours.  Additionally limited off roadway work will be performed Monday - Friday during the daytime hours.

Overhead utility replacement:  

This work continues daily between 7AM and 7PM on Central Avenue eastbound  and westbound between the west City line and Colvin Avenue.  The contractor for National Grid is working off roadway to set new utility poles.  Minimal impacts to the eastbound traffic during this work.

Various other overhead utility companies will have right eastbound or westbound lane closures between 9AM and 3 PM daily to relocated their utility lines. 

 

 Courtesy of: 

 

William E. Trudeau Jr.

Coordinator

City of Albany

Traffic Engineering

526 Central Avenue

Albany, New York 12206

 

No comments:

A BLOG FOR CENTRAL AVENUE ALBANY

This Blog is being maintained by the Staff of Central District Management Association, Inc. This Blog also accepts contributions from writers and community members.

Managed by the Central District Management Association Inc.
176 Central Avenue
Albany, New York 12206
518-462-4300